Problem: Mole under pool deck in Colleyville. Solution: Directional bore.
The Partner: Industrial Electrical Contractor
Project Scope: Quad-run of 2-inch Schedule 40 PVC electrical conduits (totaling 320 linear feet of pipe) under an established concrete driveway and commercial right-of-way.
Depth: Set at a consistent 48 inches to clear local municipal clearance safety thresholds.
Soil Conditions: Sandy loam transitioning into rocky sub-grade.
The Solution: Navigated a highly congested utility easement using real-time walkover tracking, pulling all four conduits simultaneously in a single clean pass without disrupting traffic or damaging manicured corporate landscaping.
View groups and posts below.
This post is from a suggested group
Welcome to our group Contractor Network Chat! A space for us to connect and share with each other. Start by posting your thoughts, sharing media, or creating a poll.
This post is from a suggested group
Welcome to our group Case Study Vault Exchange! A space for us to connect and share with each other. Start by posting your thoughts, sharing media, or creating a poll.
This post is from a suggested group
Welcome to our group Utility Digging Pros Forum! A space for us to connect and share with each other. Start by posting your thoughts, sharing media, or creating a poll.
This post is from a suggested group
Welcome to our group Get It Dug 2 Group! A space for us to connect and share with each other. Start by posting your thoughts, sharing media, or creating a poll.